Project Objective
The England and Wales Census, the largest single programme of work organised by the Office for National Statistics (ONS), is a unique once-in-a-decade opportunity to get an up-to-date, comprehensive picture of the country's population. It is a high profile one-off operation, with little chance to recover, modify or change and a clear focus is necessary if the objectives of quality and timeliness are to be met. Mistakes have the potential for being costly and irreversible.
To manage such a complex high risk programme requires a sound infrastructure. The 2001 Census programme management arrangements, the subject of this evaluation, were put in place to meet these requirements. They comprised three key areas: comprehensive programme planning and organisation, a well coordinated project management structure and robust programme control procedures.
Background
The Government announced in October 1992 that planning would proceed on the assumption that the next Census would be held in 2001. The decision followed a UK wide review, Census Policy Evaluation and Re-appraisal (PEAR), which confirmed that there would be a continuing need in both the public and private sectors for the type of information provided by a census and that there were no alternative sources.
The 2001 Census programme was subsequently launched in 1993-94. This was at an earlier stage than for the previous census, in recognition of the National Audit Office's 1991 Census Review finding that development and planning had started too late, resulting in extreme pressure to complete preparation in a timescale, which might have led to errors and wasted resources. At an early stage strategic aims for the Programme were identified and adopted to provide direction and goals, following and early assessment of requirements from the PEAR and a major survey of 1991 Census users, conducted in 1994.
As for the previous census, the 2001 Census programme was planned and conducted around four phases: a research phase reviewing options and proposed new topics; an assessment of options in a public test in 1997; a prototype for 2001 in the Census rehearsal; and 2001 Census production.
ONS worked in close liaison with the other two offices responsible for censuses across the UK, the General Register Office Scotland (GROS) and the Northern Ireland Statistics and Research Agency (NISRA). Although the three Census Offices operate under legal and administrative processes which differ to some extent, they agreed at the outset that there should be no unnecessary differences in the approaches taken. The overall aim adopted was to maximise the potential for achieving an integrated approach consistent with achieving the best value for money, whilst still meeting each country's particular requirements.
The management arrangements and procedures put in place, as for the 1991 Census, were based upon the Government's PRINCE [Projects IN Controlled Environments] methodology, and were tailored for each of the different phases of the programme to best support the achievement of their various objectives.
This report focuses on programme management within ONS for the 2001 England and Wales Census. It concentrates on evaluating the effectiveness of the structures, procedures and processes that were put in place between 1996 and spring 2003. The outcomes of the projects and programme are beyond the scope of this report and are dealt with in the relevant project reports. A list of the different projects and evaluation reports/summaries is available HERE.
Methodology Programme organisation
For the first time, ONS based the Census operation totally at its Titchfield office in Hampshire. All disciplines of staff working full-time on the Census, which included statisticians, researchers, IM specialists and those providing administrative support, were brought together into one of ONS' twenty-four 'Divisions', Census Division. The core number of staff was between 100-150 with a peak, in 2001-02, of 325.
For the 1991 Census, coordination across countries had been dealt with by drawing up a formal interface agreement with GROS defining in considerable detail the respective responsibilities and contributions of OPCS and GROS. For the 2001 Census, a four tier governance structure was put in place to support the control and coordination of policy and operations across the three Census Offices and bring together the vast diversity of activities and multi-disciplined resources that contribute towards a Census. The United Kingdom Census Committee (UKCC) coordinated policy across the three Census Offices and the Census Programme Board (CPB) controlled the programme within the strategic framework set by the UKCC. Both were constants throughout the 2001 Census Programme. Below the CPB were a number of project boards, overseeing the final layer of projects making up the programme. In the time between these arrangements being set up and the Census being carried out and published, devolution was implemented, thus transferring various policy responsibilities to the Scottish Parliament and the National Assembly for Wales. Given the timing, the impact of devolution on Census plans was relatively small and could be taken account of within the existing Governance structure.
The number and scope of responsibilities of Project Boards was varied according to the demands of the different phases of work. Two project boards, Policy and Operations, constituted at the outset of the programme were subsequently supplemented by more specific Boards. For example the 1997 Test Board, the Publicity and One Number Census Boards were set up before the Census 2001 Rehearsal and the Contracts Management Board was set up after the letting of the Processing contract in 1999. Some rationalisation of the structure for the 2001 Census operations saw the closure of the Operations and Policy Boards.
In principle, all work contributing to the programme eg methodological research, systems development, operational running and quality control was to be managed within a formal 2001 Census project, commissioned and controlled within its management structure, with the objective of ensuring that the common planning and management demands were met. The division of work into projects, starting formally in 1996, also, as with boards, changed in response to the demands of the different phases of the programme. Numbers of projects varied from 9 (for the planning and the conduct of the 1997 Test) to 15 to support the Rehearsal and the 2001 Census operation, between 1999 and 2002.
A programme support office (PSO), which had a maximum of 17 staff, was put in place to meet financial and business management requirements, and to facilitate the achievement of overall objectives by ensuring that quality procedures operated, that management boards and Project Managers were supported and advised, and that staff had the understanding of the context of their own work and management arrangements sufficient to make an effective contribution within the programme management framework.
Project Management
A Project Manager, appointed to each project, was made responsible for the formal definition of the work, its breakdown into 'work packages' (smaller elements based upon the relatively short-term delivery of a key end product), obtaining resources to undertake the work, and the delivery of end products. The scope of the work managed within any project could include in-house functions and outsourced activities, the latter therefore requiring contract management.
A review of the management of 1991 Census concluded that decisions were often inappropriately delegated upwards or taken at too low a level, Management arrangements for 2001, therefore, included a new procedure to allow the key decision points to be recognised, initially by Project Managers during planning stages, and for each key decision to be allocated a level of the management structure at which it should be taken. This progress control framework was approved initially by CPB and also subject to a quarterly review to ensure that forthcoming plans were relevant.
In the time critical programme, timetabling and monitoring were crucial. Although Project Managers could plan to the degree of detail that met their own management requirements, a minimum level was required of key decisions and work packages, so that programme views would have a consistency of detail across the different activities. Programme level plans were produced by the PSO.
Project Managers were required to report formally to their owning Project Boards both regularly (in the form of Highlight reports), and in response to a deviation from an approved plan (Exception Reports were also produced independently and submitted to each level of board by the PSO.
Project software, initially Microsoft (MS) Project 4 replaced by MS Project 98 after the 1997 Test, was used for planning and the recording of progress at the project level, and to create programme views.
Programme Procedures
The approach to the control of programme business within the overall strategic aims and its supporting detailed framework of objectives and timetabled deliverables was refined and the associated procedures, identified below, defined and rolled-out in advance of the Rehearsal. Procedures were essentially paper-based at the outset but electronic facilities were used to a varying degree as they became available.
Change management
Change management procedures (CHAMPS) were put in place to ensure that the impact of the inevitable potential changes, arising from both inside and external to ONS, were thoroughly assessed, decisions taken at an appropriate level and, if adopted, made in a planned and systematic manner.
The management of change covered work undertaken both within ONS and by service providers and the procedures involved stages to uphold contractual requirements.
Issue management
Issue management procedures (IMPs) were introduced to support a full assessment and any necessary discussion of impact, their resolution at the appropriate level and the communication of outcomes. For 2001, a conscious effort was made to involve all levels of staff in the identification of issues to help ensure their early recognition and resolution.
Risk management
A risk management framework was also developed specifically for the Census and extended to outsourced services. The procedures allowed for the identification and documentation in risk registers, of risks emanating from internal and external sources, the necessary contingency planning, and for the appropriate communication and management. A senior management post of Risk Manager was introduced in 2000 to ensure risks were regularly reviewed and action taken as necessary.
Financial management
Funding provision for the programme, in total some £207 million, was obtained through the Government's Public Expenditure Surveys (PES)/Comprehensive Spending Review (CSR). Final plans for the 2001 Census were endorsed and funding awarded as a result of a business case in CSR 1998. Two financial objectives, relating to achieving greater overall benefit from tax payers investment and maximising the potential for joint ventures and partnerships, underpinned the business case and guided the programme direction.
Financial management functions to meet the requirements of ONS and the Treasury as well as those from within the programme were co-ordinated by PSO, engaging with Project Managers.
Assessment & Lessons Learnt Programme organisation
The accommodation on one ONS site of all staff working full time on the programme yielded positive advantages in terms of the ease of communications at the working level within project teams and with the delivery of training to all project staff. The down side may have been a diminution in communication and issue resolution between Census Division and the parts of ONS based elsewhere, particularly the London based ONS senior management.
The management structure adopted, with representation from GROS and NISRA at each level, allowed for the necessary coordination across the three Census Offices. This generally provided an effective framework for UK governance. There are, however, two lessons to be learnt. One is that the resource needed to implement the different requirements for the 3 offices was governed by the complexity of the different requirements rather than the volume of records to be processed. For the future, it is possible that requirements will differ more as devolution becomes more embedded. It is likely that future governance arrangements will need to be adapted to take account of the impact of devolution; for example, it is already clear that a more specific role for the representation of Welsh interests will be required. Appropriate governance and funding agreements will need to be put in place at the outset to recognise any different requirements and reach agreement regarding their impact on resource contributions. The second lesson is that the UK governance structure in 2001 meant that there was no framework solely for the governance of the England and Wales Census, a factor which should be considered in any future arrangements.
The composition of the groups of Project Boards in place at the various stages did not always allow for the required operational focus nor provide for an effective level to co-ordinate inter-project activities beneath the CPB. Advantage might have been gained, for instance, by having a board or sub-group of the CPB specifically to coordinate the rehearsal phase, mirroring the successful approach taken for the 1997 Test. The continuance of the Operations board throughout the cycle could have generally enhanced the co-ordination of activities during the 2001 Census operation phase by providing a forum to take decisions, including those to resolve issues.
The inclusion of the vast majority of the various aspects of work into formal projects allowed the requirement for a common approach to the standards of planning and management to be promoted and achieved.
The actual division of work into projects was based in practice upon as close as possible alignment with the existing line management function based structure. Whilst this may have had the potential to reduce any detrimental effects inherent in 'matrix' management, it possibly lead to more projects than necessary being commissioned, placing an increased demand upon the requirement for project management skills and management of interfaces, and did not perhaps promote the building of multi - functional teams required in the majority of projects. Whether or not to define projects along line-management lines should be looked at again for future Census work.
The PSO function proved effective in co-ordinating business and financial management activities and in providing the required support to Project Managers, in administering procedures, in providing higher level programme views and in the provision of independent reporting to support decision management at the different board levels. The Induction course and pack for all new staff, together with a series of briefings and displayed information, successfully promoted the necessary contextual background to the work. Initially, the programme management arrangements were successfully launched by a series of workshops and described in a generally available comprehensive Programme Handbook. However, there is some evidence, including Internal Audit (KPMG) observations in a May 1999 report about the key decision process and reporting (see next section), that the arrangements would have benefitted from some enhancement in profile and understanding, perhaps generated from refresher briefings or direction from senior management.
Project Management
Project Managers and their assembled teams were able, with the organisations they established and the available expertise, meet the majority of project objectives. External consultants however needed to be brought in to support contract and risk management activities, as this expertise and experience was not sufficiently available. An early assessment should be made for any future operation as to the extent that internal resource needs to be supplemented, so that the organisation can be put in place prior to the Rehearsal.
Criteria for decision taking levels within the key decision management process and guidance on the process itself was supplemented following an Internal Audit report in May 1999, which found that greater clarity and appreciation amongst all staff working in the programme was necessary to ensure its objectives would be met. Overall, the planned structured approach to management within a framework of key decisions allowed for the appropriate level of decision taking to take place, remedying the problems of the 1991 Census.
Comprehensive plans were compiled with the appropriate level of detail identified for each project. This allowed for the required programme level reporting and views of interdependencies providing the context for assessments of impact across projects. On a practical side, the structure of the plans could have been more uniform to ease the production of programme level reports.
The Internal audit report mentioned above, whilst endorsing the procedures themselves, revealed a perception at the project level that the reporting requirements in place were excessive, which had the potential for reducing effectiveness. As a consequence, some small changes were introduced but overall the regularity and content of reports were judged fundamental to the essential monitoring and control of the programme.
The project software used (MS Project) allowed a productive balance to be struck between ease of use and richness of features.
Programme procedures
Change management
Nearly 600 requests to change (RFCs) were logged into the CHAMPs, with 250 of those necessarily involving service providers. Whilst generally successfully embedded in the culture of the programme, particularly for changes with direct contract management implications or arising from IM operational requirements, there will remain the challenge in any future programme of uniformly harnessing all the diverse range of activities.
The stages of the process effectively supported the overall objectives regarding the control of change, including contractual requirements. Additionally, the information identified and quantified in the course of the progression of RFCs proved to be an invaluable source in wider aspects of contracts management.
The introduction of an electronic based system, identified as being potentially beneficial to the progression of RFCs, did not come to fruition because of resource availability and compatibility problems across the Census Offices. An electronic system should be set up at the outset of any future programme to streamline the process and consideration should also be given to enabling access by service providers.
Issue management
Issue Management procedures worked smoothly as a process but were little used (only 13 issues formally raised) in the context of the number of issues arising which affected more than one project. The use of a common approach to issue resolution would have minimised the risk to the timeliness and coverage of assessments, promoted relevant discussions of impact, supported controlled decision taking and helped to communication outcomes.
Any future programme would benefit from a more structured approach to the resolution of issues, facilitated by a supportive procedure and, perhaps, dedicated senior management resource, along the lines of the approach taken this time for Risk management.
Risk management
An Internal Audit report (June 2001) concluded that the controls in place were sound. Recognition was given to the value of the Risk Manager post along with the procedures to support an ongoing assessment process and formal documentation.
This overall view was enforced by the National Audit Office (NAO) report 'Outsourcing the 2001 Census' (October 2002) which concluded that the ONS had established a robust risk management framework.
Financial management
The expectation is that the Census will be delivered within the overall budget of £207 million. Maximising the potential for entering into joint ventures in order to achieve value for money improvements has resulted in a greater range of outsourced activities than for previous censuses to the value of nearly £80 million, just under 40 per cent of the total.
The systems adopted to manage the co-ordination of financial planning, monitoring and reporting were the subject of regular internal audits (the last in January 2002) and were found overall to be sufficiently robust to enable both internal programme and wider requirements to be met.
Conclusion
The management arrangements put in place, as described above, have collectively provided an infrastructure which overall has allowed for the necessary focus of direction and control to meet the demands of the 2001 Census programme.
Experiences have again highlighted the particular challenge of not just conceiving and defining robust structures of management and procedures but of successfully embedding the required working practices into the culture of a complex programme with its variety of activities and disciplines of staff.